 |
Projects |
| |
The following is a short list of our
projects performed in the past few years.
- AES power transmission line, Puerto
Rico, USA
- Switch yard for
Power Plants, Texas, USA
- Bridge over I-10
@ Jourdan River, Mississippi, USA
- Super Conducting
Super Collider, Texas, USA
- US 59 @ BeltWay
8, Texas, USA
- I-40 @ Rio
Grande River, New Mexico, USA
- Maraven / PDVSA
Refinery, Venezuela
- Pharr / Reinosa
International Bridge, Texas,
USA & Mexico
- Lake Lewisville
Intake Str. & Bridge, Texas,
USA
- Tren Urbano,
Puerto Rico
|
|
 |
Project: AES
Power Plant, Guayama, Puerto Rico
Description: The
project consists of 34 drilled shafts from 48 inches
to 132 inches in diameter and 45 feet deep for high power
transmission line connecting the new AES power plant
to the existing Puerto Rican grid. The work was carried
out through a variety of soil conditions, from very soft
soil to very hard rock. Work areas were from sea level
up to several miles in to the mountains. 132 inches diameter
drilled shaft were required to install two monopoles
to clear existing high power lines. Whole scope was completed
in six (06) weeks.
General Contractor: Duke Engineering & Services a Duke Energy Company.
Owner: AES Corporation a Global Power Company.
Location: Guayama
Puerto Rico.
 |
 |
| Tower 10E and
10W are 132 inches in diameter by 40 feet deep drilled
shafts. About 30 feet of silts-gravels and soft clays
and 10 feet penetration into hard rock. a 14 to 18
feet long permanent casing was used in the upper
part to protect the integrity of the shaft while
drilling. |
 |
 |
|
 |
 |
| The
remaining are four (04) leg tower as shown above.
Diameter ranged from 48 to 96 inches and between
15 to 35 feet deep. |
|
| |
go to top |
|
 |
Project: Brownig
lake power plant expansion project and TENASKA-GATEWAY
845-Megawatt Combined-Cycle Facility, Mt. Enterprise,
Texas
Description: These
two projects consists of many drilled shaft foundations
to support all the different equipment required for each
project switch yard. A.H. BECK provided both project
with a turn key foundation construction package.
General Contractor: a
J.V. between Black & Veatch and Zackry construction corporation on both projects.
Owner: CPS of
San Antonio and TENASKA
Location: San
Antonio and Mt. Enterprise, Texas.
 |
 |
San Antonio
CPS switch yard pictures. |
 |
TENASKA
gateway switch yard picture. |
|
| |
go to top |
|
 |
Project:
Replacement of bridge over Jourdan river , Gulfport,
Mississippi.
Description: This
project consists of 97 drilled shaft foundations 60 inches
in diameter, between 90 and 113 feet of depth. Scope
includes an Osterberg cell load test for design verification.
General Contractor: L & A
Contracting Co.
Owner: Mississippi
Department Of Transportation
Location: Gulfport, Mississippi
|
| |
go to top |
|
 |
Project: Super
Conducting Super Collider Tunnel Access Shafts
Description: Project
consisted of installing 14 tunnel access shafts varying
in diameter from 18 to 28 feet and depths to 270 feet.
Also secant piles were installed down to into the rock
to stabilize the overburden.
Owner: DOE
- US Department of Energy
Location: Waxahachie,
Texas
|
| |
go to top |
|
 |
Project: US
59 intersection with Beltway 8
Description:Project
consisted of 142 drilled shafts up 120 inches in diameter
and 100 feet deep. Due to the lack of room in between
existing US 59 main lanes the designers had to use single
large diameter and deep drilled shafts and single column
design to support the upper structure. The reinforcing
cadges for these shafts where up to 120 feet long and
weighting up to 40,000.00 pounds. The shafts were excavated
using Bentonite and the slurry displaced method of drilling
in order to stabilize the soft sandy silt soils.
Owner: Texas
Department of Transportation
Location: Houston, TX.
|
| |
go to top |
|
 |
Project: I-40
Rio Grande River Crossing
Description: Project
consisted of 88 drilled shaft 84 inches in diameter,
slurry displaced method up to 120 feet deep. Soil consisted
of pure sand and approximately 20 feet of SCG (Soil,
Gravel and Cobbles). 35 feet of permanent casing was
installed on each shaft. Due to the large diameters and
depths of the shafts 2500 bbl's ( 105,000 gal ) of bentonite
drilling mud was used on site.
Owner: New
Mexico Department of Transportation
Location: I-40
@ Rio Grande River Crossing, NM
|
| |
go to top |
|
 |
Project: Maraven/PDVSA
Cardon Refinery Upgrade, Venezuela.
Description: Project
consisted of about 2400 drilled shafts up 64 inches in
diameter and 45 feet deep. Due to the lack of room in
between existing pipe sleeper ways trenches, engineers
had to use drilled shafts design to support a variety
of structures ( new piperack, power & control cable
bridges, conveyors, cooling water pipes support, etc.),
above the old pipe trenches or beside the cooling water
open discharge channels. The shafts were excavated using
dry method of drilling on a very high compacted caliche
soil with strenth up to 400 Kg/cm2. It was necessary
custom tailored long reach drilling rigs to drill up
to 90 feet away from the access roads and over the existing
pipelines. Top production was 125 completed drilled shaft
per week using two (2) units, and a total duration of
nine (9) months.
Owner: Maraven
/ PDVSA
Location: Cardon, Venezuela
|
| |
go to top |
|
 |
Project: Pharr
/ Reynosa International Bridge
Description: Project
consisted of 400 - 60" diameter 60'deep slurry displaced
drilled shafts extending from the Rio Grande river, 3
miles into the interior of Mexico.
Owner: Grupo
Marhnos, Mexico.
Location: Reynosa, Tamaulipas,
Mexico
|
| |
go to top |
|
 |
Project:
Lake Lewisville Intake Structure & Bridge
Description: Project
consisted of 12 drilled shafts, up to 52 inches in diameter
and 110 feet deep. This foundations give support to the
water intake structure, the water pipeline and the access
bridge to the intake structure. Soil layers consisted
of clay and sand over a sand stone. Casing and Slurry
displaced method were used to keep integrity of holes,
with 50 feet of water depth. Penetration up to 10 feet
in to the 14,000 PSI sand stone using recirculation drilling
method. Concrete for the project was pumped from the
dam, 550 feet away.
Owner: Upper
Trinity Regional Water District.
Location: Dallas, TX.
|
| |
go to top |
|
 |
Project:
Rio Piedras Section of the Tren
Urbano - Puerto Rico
Description: The
project consists of 1018 drilled shafts up to 48 inches
in diameter and 92 feet deep as part of the temporary
structures to support the main shafts massive excavation.
The very tight work area has forced the use of soldier
piles and lagging to protect adjacent building around
excavation areas.
General
Contractor: KKZ/CMA jv. - Kiewit - Kenny
- Zachry / CMA.
Owner: Tren
Urbano - Department of Transportation and Public Works -
DTOP
Location: Puerto
Rico.
|
| |
|
|
 |
|
 |
Services |
| |
Foundation drilling specialists in a broad
range of applications: Commercial / Industrial Structures;
Slurry drilling construction; Over Water; Limited Clearance/Access;
Highways and Bridges; Large and Small specialty drilling; Tunnel
Shaft. |
| |
 |
 |
Contact Us |
| |
For more information please call or email
us. |
| |
 |
|